Arguably, the most consequential phenomenon in the history of building construction continues, with no apparent end in sight. The ability to now measure this phenomenon represents a significant analytical breakthrough—one that provides the insight necessary to mitigate the risk of construction contributing to a financial downturn of a magnitude not seen since the 2008 subprime mortgage crisis.
The data clearly shows, for example, that instead of the tens of millions of dollars in excessive cost, several healthcare systems are now paying hundreds of millions more than necessary on a single hospital project.
Recent, compelling data findings and analysis show a strong correlation between these extraordinary costs and the growing adoption of Integrated Project Delivery (IPD). The analysis is simple. IPD has taken cost-plus and billable hour compensation scope from the 1st tier builder to the 2nd tier trade contractors and prefabrication providers.
Decades of growth in construction management (CM), that applies first-tier cost-plus and billable-hour compensation models, have correlated to a sustained trend of cost escalation exceeding national inflation.
IPD began to grow throughout the 2000s and 2010s, starting with the mechanical, electrical, plumbing (MEP) trades and then expanding to other trades and incorporating prefabrication assemblies.
As IPD gained traction the cost-plus and billable-hour scope expanded - from less than 10% of the project (1st tier builder) - to more than 50% (2nd tier and Prefab) in many case - a surge in owner cost burst forth starting a few years prior to the Covid pandemic.
A universal maxim is at the core of the problem: you get more of what you reward. Cost-plus and billable-hour compensation rewards higher costs and more billable hours. It was bad enough at the first tier (CM), but the situation is now being pushed to alarming and unsustainable levels by extending it to the second tier through the growing adoption of IPD..
IPD should and would provide an effective and efficient design and delivery approach if the misaligned compensation structure were reversed. The financial motivation needs to be flipped in order for the return-on-effort to be aligned with the intrinsic motivation to produce customer value through operational excellence.
This is the 24th article in an in-depth series examining the construction industry’s persistent stagnation and the seemingly inexorable escalation of costs now accelerating under IPD. The series explores the background, underlying causes, and systemic failures driving these problems. They go on to develop the origins and propose solutions capable of redressing them at their roots. Explore the full series at Building CATALYST Insights.
The solution essentially translates W. Edwards Deming's work in manufacturing to construction - and the development of the Construction as a System (CaaS) alternative to today’s fragmented and stagnated state. His win-win management philosophy, complexity science and knowledge system transformed Toyota and manufacturing. The same philosphical and technical breakthroughs can now be applied through CM, IPD, and Design-Build delivery approaches to reverse the misaligned compensation framework while infusing automation and operational excellence.
The timing for Construction as a System (CaaS) is particularly compelling, as AI is creating a strategic inflection point for the construction industry—one that should help eliminate layer upon layer of billable and non-billable hours. This new system applies to consultants, designers, as well as builders and trade contractors.
The balance of this article presents the data discoveries supporting these claims.
_____________
Annual construction volume now exceeds $2 trillion in the US. Even prior to the revelation of the surge IPD-correlated cost, our industry’s decades-long productivity stagnation resulted in construction cost escalating to more than double the inflation-adjusted value for buildings1,2,3.
Our hypothesis is that further correlation-to-causation data research and analysis will enable us to measure the added impact of cost-plus and other current practices across all building sectors. The findings so far, from an in-depth data analysis of 37 hospitals, indicate a great looming construction failure.
Continued macroeconomic and microeconomic research is needed to determine how many billions of dollars over inflation are being extended annually on hospitals. Yet, despite growing public concern over the rising cost of healthcare, there is virtually no discussion about the contribution of hospital construction to that burden.
Where health systems fail to push back, building teams applying these practices are essentially being given a blank check. The growth of negotiated trade partnering across other market sectors necessitates a broader scope of data collection and research to assess its impact at the national level.
An Examination of Critical Data Discoveries
Let’s look at the essential findings of the hospital data research and analysis. Among the dozens of metrics available, we will focus on three key indicators: Cost per Operating Room; Mechanical, Electrical, and Plumbing (MEP) Costs; and Indirect Costs—including the builder’s General Conditions (GC), General Requirements (GR), Overhead (OH), and Profit.
As shown in Figure 1, an operating room (OR) would cost approximately $2.2 million if its construction cost had increased only at the rate of national inflation. If costs had instead risen at the average rate for all building sectors (per published Construction Analytics data), the same OR would cost approximately $4.7 million—more than twice the inflation-adjusted estimate.²˒³ However, the data analytics reveal that actual OR construction costs have risen substantially beyond both benchmarks. A strong correlation in the data indicates that health systems are paying from nearly three to more than five times the amount justified by inflation.

The financial incentive to design, budget, and build projects at the highest allowable cost is a fundamental problem that must be redressed.
Every trade is influenced by misaligned incentives. Although negotiated trade partnering is intended to improve owner value, the data indicated that these practices produce the opposite effect. The MEP trades are usually the first partnerships to be engaged. In Figure 2 we see the MEP cost trend that shows why operating rooms, like every other hospital function (aka key planning unit (KPU)), is escalating beyond imagination.

Finally, let’s examine the trend in indirect costs. When expressed as a percentage of direct costs, the growth in indirect costs does not appear as alarming. However, because these practices drive direct costs upward, a more meaningful metric for evaluating indirect cost growth is the cost per finished square foot (SF). Figure 3, therefore, reveals a similarly steep upward trend in builders’ general conditions and requirements, permits, insurance, bonds, overhead, and profit.

By 2025 annual construction volume in the US crossed $2 trillion mark, of which half was over-inflated. To put into perspective - that our now $40 trillion in national debt is growing by up to $3 trillion annually – construction waste and abuse could equate about half.
The well-intentioned IPD movement has helped projects run more smoothly, reduce claims and disputes, and improve the likelihood of making on-time, on-budget delivery claims. Many of its core practices—including trade partnering, early collaboration, and prefabrication—also offer real potential to reduce construction waste.
However, these benefits become detriments when coupled with a misaligned compensation framework. Cost-based, cost-plus, and billable-hour compensation models incentivize higher budgets, greater spending, and increased labor demands rather than cost efficiency, innovation, and the achievement of measurable value outcomes.
A proposed Value-based Contracting System (VCS) redresses the compensation problem by combining impartial market intelligence with a framework designed to reward measurable improvements in value and efficiency. We explain the approach in The Case for Construction as a System.
The big question is whether owners and industry leaders are willing to change the compensation practices that sustain excessive costs, even when doing so challenges established profit generation frameworks.
If owners and leaders are willing to change, then the other benefits that IPD provides will be enhanced. The Design-Build approach provides a more inherently integrated framework. The Design Build Institute of America (DBIA) provides the framework, network, and resources. Our DBIA blog post The Need for Highly-automated, Systems-based Design-Build presents an alternative worth considering.
Our primary construction reform goal for 2027 is to identify and help equip leaders willing to examine the data, test proposed solutions, and advance meaningful reform on one or more projects currently in early planning or design.
We just need a few owners, owner-advisors, architects, engineers, builders, educators, and researchers who will bring their knowledge and professional judgment to this effort.
Reform requires courage and conviction expressed through action: questioning accepted practices, demanding credible evidence, and holding ourselves accountable for the value we deliver.
To learn more, visit www.buildingcatalyst.com.
End Notes:
1 Building CATALYST - Applying MVA (multivariate analysis) in March and April 2026 - CATALYST performed micro-economic analysis of 35 hospital projects, spanned multiple regions, owners, designers and builders, with project data anonymized for confidentiality. These project ranged in stages from a comprehensive budget / target value to final completion. Two hospital projects have since been added that show continued excessive escalation.
2 Bureau of Labor Statistics (BLS), "Producer Price Index (PPI) for Construction Inputs and Employment Cost Index (ECI)," U.S. Department of Labor (1970–2026).
3 Ed Zarenski, Construction Inflation 2025 Update (Nov), Construction Analytics, November 13, 2025.